SITE DESCRIPTION
Treated Volume | 4,050 m³ of contaminated soil (7,290 T) |
Thermal technology | In-Situ Treatment (ISTD, full scale) |
Main contaminant | PCB (polychlorinated biphenyls) |
Site challenges | Former cathode/graphite manufacturing site (1938-2008); perched groundwater at 2.5 m required a concrete cut-off wall around the treatment area |
Project Timeline | 2013 - 2014 |

SOLUTION
Treatment Method |
Full-scale In-Situ Thermal Desorption, 4 batches of 22.5 x 10 x 4.5 m |
Treatment program | 92 heating wells, target temperature 250°C |
Contaminated Vapors Management | Oil-water separator, liquid-phase granular activated carbon (GAC) and GAC vapor filter |
Process control | Dewatering, then ISTD heating, then vapor recovery/condensation · thermocouple monitoring of subsurface temperatures |

RESULTS
✅ 4,050 m³ of contaminated soil treated (full scale). |
✅ Guaranteed-performance contract target of below 10 mg/kg PCB pursued under French Permanent Solution norms |
✅ Project delivered as a turn-key design, construction and operation contract for Carbone Savoie (Rio Tinto Alcan Group) |