Xinxin – China

Context

The site is located in the Province of Gansu in People’s Republic of China, near the town of Qingyang. The treatment zone is in an industrial area. The contaminated soils come from various sites in the region.

external
external

Project Description

The project is setup in a hangar on a surface of about 250m² with 9 diesel burners and a vapor treatment unit. The treatment area is impacted with various solvents. The targeted concentration at the end of the treatment is 3000 mg/kg. The treatment began on July 27th, 2017 and ended on October 27th of 2017, which gives a total treatment time from the beginning of 90 days.

Before the build-up of the pile, stability tests were done with different types of soil to select the appropriate wetness and consistency of soil to build the pile. Since the pile was build up in a hangar, the access to the pile was limited. During the building of the pile, different layers of more or less contaminated soil were setup. The ESTD treatment facility was set as shown on the picture below.

Planning

  • Installation: From 13th of July to 20th of July
  • Treatment: From 27th of July to 27th of October
  • Analyses & reports: 1 week
  • Demobilization: From 27th of October to 10th of November

Monitoring

external

Wuwei project has been a challenging project due to:

  • The first project in China
  • A new partner: shared preparation and work in an intercultural context
  • New technics and methods
  • Contaminants and concentrations which caused corrosion issues
  • The use of water retaining walls without water pumping during the treatment

The project ends as a success (targets completed): temperatures were not able to go above 100°C in most of the monitoring points but the stripping process decontaminated the soil. The blower from the vapor treatment unit was not appropriate for the project but the vapors were well condensed and treated.

Condensate Recovery

external

The contaminants extracted from the soil were recovered from 2 different knock-out setup in the vapor treatment unit. The first knock-out was installed between the vapor collector and the heat exchanger. The liquids were pumped out of the tank on a daily base. The second knock-out which was installed after the heat exchanger was emptied manually into the first knock-out. The liquids were recuperated by the client. The graph below describes the amount of condensate (water + contaminant) recovered from the soil during the heating process.

A total of 30,4m³ of liquids was recovered from the soil during the heating process. With a total treatment volume of 217m³ this means 14% of the liquids in the soil were recovered. The volume of liquids recovered at the end of treatment was still around 100L per day. This means that the soil was still contaminated.

During the treatment, liquids categorized as paraffines came out of the pile through the holes around the tubes. Since the amount of liquids was very important, a brick wall was built to protect the multiple networks and to recover the liquids. The graph below shows an estimation of the paraffines recovered from the pile over time.. 

external

Conclusion

The oil content was drastically reduced. More than 70% of the contaminants were extracted from the soil. The contaminant concentration in the treated soil is below two of the three target levels of contamination (respectively 20 000, 10 000 and 3000 mg/kg). Treating the soil for a longer period and/or optimizing the treatment for heavy impacted soils such as sludges would reduce the concentration below 3000mg/kg. From challenge to success, many issues (technical, operational and communication) have been faced and answered which must be recorded as lessons learned for the next projects. 

Key Data

Contaminants
TPH

Max. Concentration
150 000 mg/kg DM

Volume
217 m³

Tonnage
340 Tons

Nb of Heating Tubes
Burners: 9

Exchanger Tubes: 3

Vapor Tubes: 12

Temperature Target
220°C

Heating Duration
33 days

Treatment Targets
3000 mg/kg DM

Location
Xinxin, Gansu – China

Future Use
Industrial

Client
Vision & Action

Partner
Vision & Action

Date
2017

Skip to content