SITE UPDATE: ESTD IN STRASBOURG, FRANCE

SITE UPDATE: ESTD IN STRASBOURG, FRANCE

 We have launched the 8th pile at our site in Strasbourg, France. We are treating polycyclic aromatic hydrocarbons and hydrocarbons by applying Ex-Situ thermal desorption (ESTD).
 
We are working in collaboration with Ortec on this project. We are bringing together our expertise to give back health to our soils!
 
We are currently in the processing phase of the remediation process. 41 burners are used and heated at 400-450°. The desired treatment temperature is at 200° and the method of treatment is by thermal conductive heating.
The works are part of the Deux-Rives / Zwei Ufer project, and under the control of the SPL Deux-Rives.